CSP practice question: Schedule recovery under the triple constraint
Question of the Day for Thursday, 3 September 2026
CSP · Program Management
Answer in HSE HUB Pro
A machine guarding retrofit must be finished by a fixed date set in an OSHA settlement, and its budget is capped with no contingency left. The schedule runs: risk assessment of each machine (done), guard design 4 weeks, procurement 3 weeks, installation 3 weeks, validation testing 1 week, then operator training 1 week. The project is now 3 weeks behind. Which recovery approach fits these constraints?
ACrash the installation by hiring a second contractor crew, since adding resources is the surest way to cut a critical path
BDrop validation testing, since the guards are built to the design and testing adds a week without changing the guards
CFast-track: order long-lead parts before design ends and develop training during installation, managing rework risk
DAsk to move the settlement date, since time, cost and scope are all fixed and no trade among them is now possible
See the answer and the full explanation
Answers to Questions of the Day stay open for 30 days. This one, and every question in the bank, is answered and explained in HSE HUB Pro: unlimited practice by domain, the full 200-question mock exam and animated lessons.
See HSE HUB ProTry today's question, answer includedStudying for the CSP? The CSP11 blueprint explained · How to get the CSP · CSP practice exam by domain · All guides
Unofficial study aid: not affiliated with, endorsed by, or connected to the Board of Certified Safety Professionals (BCSP). ASP and CSP are trademarks of BCSP. Questions are original study items written for HSE HUB.