CSP · Program Management
At a PSM-covered unit, an approved MOC adds a 3-inch bypass around a feed control valve, with a hazard review, updated P&IDs and a pre-startup safety review set for tomorrow. During installation the contractor could not get the specified flanges and fitted a lower pressure class, rated above normal operating pressure but below the set pressure of the relief valve protecting the line. What should the CSP require before start-up?

Explanation

Paragraph (l)(2) requires the technical basis, the impact on safety and health and authorization to be addressed prior to any change, and a field substitution that departs from the approved design is a change the approved MOC never reviewed. Flanges rated below the relief set pressure can fail before the relief valve opens, so normal operating pressure is the wrong test; the design rating must be restored, or a re-engineered design reviewed and approved, before start-up, and (i)(2) requires the pre-startup safety review to confirm that construction and equipment are in accordance with design specifications and that modified facilities meet paragraph (l). Updating the P&IDs under (l)(4) records the change but neither reviews nor authorizes it, and deferring the fix to a turnaround runs the line outside its design basis. Source: 29 CFR 1910.119(l)(1), (l)(2), (l)(4) and (i)(2).
Practise more questions →

See all past questions →

Unofficial study aid: not affiliated with, endorsed by, or connected to the Board of Certified Safety Professionals (BCSP). ASP® and CSP® are registered trademarks of BCSP. All practice questions are original study items and are not actual exam questions.